Start with the consequence of a stock-out
Under the calculator’s Poisson model, a finite stock level leaves some residual risk. A readily available office phone can tolerate a higher stock-out risk if a replacement can be bought locally. A critical component with a two-year lead time may warrant more stock, an expedited supplier agreement or a stock-sharing arrangement.
Compare scenarios
- Use the normal replenishment delay and calculate several candidate risk limits.
- Compare the recommended quantities, purchase costs and expected risks in the chart and table.
- Repeat the analysis using a credible emergency replenishment delay. Compare the cost of that option with the cost of more stock.
Record the decision
Have the project sponsor approve the acceptable risk and record the target, its replenishment period, and any fallback assumptions. For a contract that expresses the target as availability or an interval between shortages, use the goal conversions.