How to model parts discarded on failure

Use the time it takes to buy and receive a replacement when failed parts are discarded.

1 min read

On this page

Use replacement lead time

When a failed part is discarded and a replacement can be purchased, enter the time from initiating replenishment to receiving usable stock in Repair Delay (Days). Forecast demand over that period using normal operating and reliability inputs.

Worked example

InputValue
Fleet160 helicopters, each with 2 GPS amplifiers
Daily operating hours4
MTBF and NFF ratio250,000 hours and 5%
Replenishment delay180 days
Unit cost and MTBSO target$4,750 per amplifier and 100 years

The calculator recommends 4 spare amplifiers for $19,000. If replacements will be unavailable for the remaining service life, use the lifetime buy approach.