Why use an interval?
A target such as 95% availability needs a time period to be useful. Mean time between stock-outs (MTBSO) combines the replenishment delay and the probability of a stock-out into one figure that project teams can compare with other service targets.
Calculate the interval
Divide the replenishment delay by the probability of a stock-out. With 95% availability and a 30-day delay, the stock-out probability is 0.05 and the expected interval is 30 ÷ 0.05 = 600 days, or about 1.64 years.
Interpret the result
An MTBSO of two years corresponds to about five stock-outs over ten years on average, assuming conditions stay the same. Actual events can cluster or be further apart. See how to convert targets if your requirement uses a percentage.